Thursday, 3 September 2020

The en suite - start Wednesday 2nd September

 No trip to New York this year so decided to finally get our en suite, bathroom, laudary and toilet renovated.  Got a quote from Craig Baskeyfield of Bespoke Bathrooms.  The quote was cheaper than the quote we got a couple of years ago so away we went.  The quote arrived on 20th July so we had to pick the fittings.  Tough job with so many choices but got it all done.  Set to start late August, eventually kicked off on the 2nd September.

These are the before photos Wednesday 2nd September -







By the end of the day damage had been done.








Insulation




Sheeting Day 2 




Waterproofing day 3





Tiler came in on Tuesday 8th September, laid the cement on day one


The floor on day 2


The walls on day 3



Grout on day 4 - tiler finished Friday the 11th September.



Painting Thursday 17th


Almost done by Friday the 18th (16 days since the start), just need the mirror and the shower glass



Finished 29th February






Before and after

 Started 2nd September, finished 19th October.